Transcription by David Wheeler
This part of the log was written by William S. Renwick,
chief engineer of the EDSAC Project headed by Maurice
V. Wilkes. Later parts were written by other engineers,
users, and operators.
Notation
The start of the EDSAC log
1949
- May 6th
- Machine in operation for first time.
Printed table of squares (0-99), time for programme 2
mins. 35 secs. Four tanks of battery 1 in operation.
- May 7th
- Machine still operating, - table of squares
several times. Table of primes attempted - programme
incorrect. Necessity for another amplifier in
Distributing Unit 3. ( Panel 37 ) noted. Coder 3
(Panel 68 ) finished.
- May 9th.
- Still operating - corrected programme for
table of primes tried successfully - machine operating
for 1 hour 58 mins. during which primes up to 1500
were calculated and printed [Programme included no
short cuts and employed subtraction only.]. No faults
and still operating in afternoon. Primes up to
4759 calculated in 40 mins.
- May 10th.
- Still operating. Battery 1 began to be
tested and wired up. 3 Panels 1 giving trouble. In afternoon
using short cut programme Primes up to 5711 calculated in
60 mins.
"Banda" duplicating system tried on Teleprinter,
machine calculating and printing primes up to 1000,
50 copies being made of results.
- May 11th.
- Modifications to machine started. Extra amplifiers in
Distributing Unit 3 and relays for the print check order [F]
mounted and wired. Initial Input modified to supply
resetting and start pulses, also to short out Order Tank
during Initial. Machine " cleaned up".
- May 12th.
- M'ier clearing corrected. "Cleaning up" completed.
Check Print order (F) relays completed. Machine tried. Phantostron
dividers giving trouble - circuit modified to more stable form.
- May 13th.
- Modifications continued.
- May 14th.
- Modifications continued.
- May 16th.
- Modifications Continued.
- May 17th.
- Clock Pulse generator U.S.
- May 18th.
- Photograph in the morning. Clock pulse generator
temporily in service. (New C.P.G. designed )
- May 19th.
- Demonstrations of squares tape in afternoon.
Half-adder giving trouble.
- May 20th.
- Computer "vetted".
- May 21st.
- Trouble with right shift - no "ones" being added when
number negative.
- May 23rd.
- Right shift corrected. Machine operating. Primes from 7
tape tried - [programme wrong ?] First battery wired
up ready to try. Monitors more permanently wired.
- May 24th.
- Coder III tested and wired in. Breakthrough of input
to wrong tanks traced. -[ due to parasitics ?] Grid
stoppers
increased to remove oscillations.
- May 25th.
- Due to delays in amplifiers in Transfer Units a 1 minor
cycle tank in Transfer necessary. Modifications to
Transfer
unit carried out.
- May 26th.
System of transfer changed to I. 1/2
- minor cycle tanks. Mods carried out to Transfer Unit.
- May 27th.
- Transfer unit modified and wired in, also 1/2 adder in F
order tank.
- May 28th
- Machine in U/S condition until Sunday 19th June
due to faults in Input and Output. I & O emitting 2
or more E/P's occasionally. Noisy panel I in Transfer
Unit - zero restorer in half-adder and 1/2 doz valves
of various descriptions.All panel I's same now 5%
resistors in strategic places ( vide circuit
diagrams ) Panel 1 in S.C.T. ( loose valve base) changed.
Also fault due to "1" timing "G" order to
S.C.T. ( 2 being added due to failure of suppression in
1/2 adder )
- June 20th.
- Machine operating. Co-ordinating orders tried ( O.K.)
Print squares ( 2 routines ) and primes from 5. ( All
O.K.) Teleprinter line feed sticky also carriage return.
Preparations for demonstrations begun.
- June 21st.
- Distributeing Unit VI ( p.51) cleaned up in morning
, also Teleprinter oiled etc. Squares tried in morning
(O.K.). E/P relay Output changed. Sticking troubles.
- June 22nd.
- Machine operating well. EF55 in D.U. VIII down.
Sticking relays.
Demonstrations.
- June 23rd.
- Demonstrations. - O.K. Symposium
1st European computer conference !
- June 24th.
- Demonstrations. - O.K. Symposium
- June 25th.
- Holiday.
- July 4th
- Modifications to Input and Output E/P system.
ETC.
The margin note appears to have been added later.
- Battery
- A set of 16 mercury delay lines
each used to store 16 35 bit words. The EDSAC commissioning
started with 4? mercury delay lines,
giving 64 full words. The full set was two batteries.
- Panel
- An electonic chassis wired into a rack.
It contained 10-20 valves, the only pluggable
units. The EDSAC had three rows of racks, each row had
three or four
racks and each rack had up to ten Panels.
- Tank
- Another name for a single mercury filled
delay line.
- M`ier
- An abbreviation for Multiplier Unit.
- E/P
- End pulse used to start the next order, For
input and output it was derived from a mechanical contact
which caused design problems.
- Valves
- (USA Tubes ) An electronic amplifying
device. A cylinder about 1 inch in diameter and 2
inches long, with up to 8 pins at one end for plugging
into a socket. They had a life of a few thousand hours.
- EF55
- A valve made by Mullard, used in EDSAC.
- Grid stopper
- A resistor connected to the grid
of a valve intended to prevent parasitic oscillations.
|